|
Part I - Programme
Objectives and Guiding Principles
1 Introduction |
 |
1.1
Rural Road Connectivity is not only a key component of Rural
Development by promoting access to economic and social services
and thereby generating increased agricultural incomes and
productive employment opportunities in India, it is also as
a result, a key ingredient in ensuring any sustainable Poverty
reduction Programme. Notwithstanding the efforts made, over
the years, at the State and Central levels, through different
Programmes, about 40% of the Habitations in the country are
still not connected by All-weather roads. It is well known
that even where connectivity has been provided, the roads
constructed are of such quality (due to poor construction
or maintenance) that they cannot be categorised as All-weather
roads. |
1.2 With a
view to redressing the situation, Government have launched the Pradhan
Mantri Gram Sadak Yojana on 25th December, 2000. The Pradhan Mantri
Gram Sadak Yojana (PMGSY) is a 100% Centrally Sponsored Scheme.
50% of the Cess on High Speed Diesel (HSD) is earmarked for this
Programme.

|
|
2
Programme Objectives |
2.1
The primary objective of the PMGSY is to provide Connectivity,
by way of an All-weather Road (with necessary culverts and
cross-drainage structures, which is operable throughout the
year), to the unconnected Habitations in the rural areas,
in such a way that Habitations with a population of 1000 persons
and above are covered in three years (2000-2003) and all Unconnected
Habitations with a population of 500 persons and above by
the end of the Tenth Plan Period (2007). In respect of the
Hill States (North-East, Sikkim, Himachal Pradesh, Jammu &
Kashmir, Uttaranchal) and the Desert Areas (as identified
in the Desert Development Programme) as well as the Tribal
(Schedule V) areas, the objective would be to connect Habitations
with a population of 250 persons and above. |
 |
2.2 The PMGSY
will permit the Upgradation (to prescribed standards) of the existing
roads in those Districts where all the Habitations of the designated
population size (refer Para 2.1 above) have been provided all-weather
road connectivity. However, it must be noted that Upgradation is
not central to the Programme and cannot exceed 20% of the State's
allocation where Unconnected Habitations in the State still exist.
In Upgradation works, priority should be given to conversion of
fair weather roads to all weather roads in the Core Network.

|
|
3
Guiding principles of PMGSY and Definitions |
|
3.1 The spirit
and the objective of the Pradhan Mantri Gram Sadak Yojana (PMGSY)
is to provide good all-weather road connectivity to the unconnected
Habitations. It must be ensured that provision of New Connectivity
(i.e., connecting unconnected Habitations) should be given precedence
in keeping with the objectives of the Programme.
3.2 Para 2.1
above refers to Population size of Habitations. The population,
as recorded in the Census 2001, shall be the basis for determining
the population size of the Habitation and the District Rural Roads
Plans and Core Networks shall be drawn up / revised on this basis.
3.3 An Unconnected
Habitation is one with a population of designated size
(refer to Para 2.1 above) located at a distance of at least 500
metres or more (1.5 km of path distance in case of Hills) from an
All-weather road or a connected Habitation.
3.4 The Unconnected
Habitations are to be connected to nearby Habitations already connected
by an All-weather road or to another existing All-weather road so
that services (educational, health, marketing facilities etc.),
which are not available in the unconnected Habitation, become available
to the residents.
3.5 The unit
for this Programme is a Habitation and not a Revenue
village or a Panchayat. A Habitation is a cluster of population,
living in an area, the location of which does not change over time.
Desam, Dhanis, Tolas, Majras, hamlets etc. are commonly used terminology
to describe the Habitations. A Revenue village / Gram Panchayat
may comprise of one or several Habitations. The population of all
Habitations within a radius of 500 metres (1.5 km. of path distance
in case of Hills) may be clubbed together for the purpose of determining
the population size. This cluster approach would
enable provision of connectivity to a larger number of Habitations,
particularly in the Hill/mountainous areas.
3.6 A Core
Network is that minimal Network of roads (routes)that is
essential to provide Basic access to essential social economic services
to all eligible habitations in the selected areas through at least
a single all-weather road connectivity.
3.7 A Core
Network comprises of Through Routes and Link
Routes. Through routes are the ones which
collect traffic from several link roads or a long chain of Habitations
and lead it to Marketing centres either directly or through the
higher category roads i.e., the District Roads or the State or National
Highway. Link Routes are the roads connecting a single Habitation
or a group of Habitations to Through Routes or District Roads leading
to Market Centres. Link routes generally have dead
ends terminating on a Habitation, while Through Routes arise from
the confluence of two or more Link Routes and emerge on to a major
Road or to a Market Centre.
3.8
It should be ensured that each road work that is taken up under
the PMGSY is part of the Core Network. While keeping the
objective of Connectivity in view, preference should be given to
those roads which also incidentally serve other Habitations. In
other words, without compromising the basic objective (covering
1000+/500+ Habitations by 2003 and 500/250+ Habitations by 2007),
preference should be given to those roads which serve a larger population.
For this purpose, while Habitations within a distance of 500 metres
from the road is considered as connected in case of plain areas,
this distance should be 1.5 km (of path length) in respect of Hills.
3.9 The PMGSY
shall cover only the rural areas. Urban roads are
excluded from the purview of this Programme. Even in the rural areas,
PMGSY covers only the Rural Roads i.e., Roads that were formerly
classified as 'Other District Roads' (ODR) and 'Village
Roads' (VR). Other District Roads (ODR) are roads serving
rural areas of production and providing them with outlet to market
centres, taluka (tehsil) headquarters, Block headquarters or other
main roads. Village Roads (VR) are roads connecting villages/Habitation
or groups of Habitation with each other and to the nearest road
of a higher category. Major District Roads, State Highways and National
Highways cannot be covered under the PMGSY, even if they happen
to be in rural areas. This applies to New Connectivity roads as
well as Upgradation works.
3.10 The PMGSY
envisages only single road Connectivity to be provided. If a Habitation
is already connected to another connected Habitation by way of an
All-weather road, then no further work can be taken up under the
PMGSY at that habitation.
3.11 Provision
of connectivity to unconnected Habitations would be termed as New
Connectivity. New Connectivity implies construction of
roads from the earth work stage to the desired specifications, and
would therefore invariably involve some earth work. In case of Hills,
it would involve Formation and Cutting. However, existing Gravel
or WBM roads will not qualify to be treated as works of New Connectivity
even where they involve some earth work by way of widening of the
Carriageway or Road formation. Work on a road which only has earthwork
(and not a Gravel Road) will be treated as a case of New Connectivity.
3.12 Upgradation,
when permitted (refer Para 2.2 above) would typically involve conversion
from Gravel or Water Bound Macadam (WBM) stage to the desired technical
specifications or widening of the roads, subject to traffic studies.
Provision of Cross Drainage (CD) works alone would also be treated
as Upgradation under PMGSY. A Gravel Road is a
road constructed using well compacted crushed rock or gravel material,
which is fairly resilient and does not become slippery when wet.
Water Bound Macadam is the road layer made of crushed
or broken aggregate mechanically interlocked by rolling and the
voids filled with screening and binding material with the assistance
of water.
3.13 The primary
focus of the PMGSY is to provide All-weather road
connectivity to the unconnected Habitations. An All-weather road
is one which is negotiable during all weathers. This implies that
the road-bed is drained effectively by adequate cross-drainage structures
such as culverts, minor bridges and causeways. Interruptions to
traffic as per permitted frequency and duration are, however, allowed.
The pavement should be negotiable during all-weathers, but this
does not necessarily imply that it should be paved or surfaced or
black-topped.
3.14 There
may be roads which are treated as Fair-weather roads.
In other words, they are fordable only during the dry season, because
of lack of Cross Drainage (CD) works. Conversion of such roads to
All-weather roads will be treated as Upgradation. Provision of only
CD works would also be treated as Upgradation. However, it must
be noted that on all the road works of the PMGSY, provision of necessary
CD works is considered an essential element.
3.15 PMGSY
does not permit repairs to Black-topped or Cement Roads, even if
the surface condition is bad.
3.16 The Rural
Roads constructed under the Pradhan Mantri Gram Sadak Yojana must
meet the technical specifications. The specifications laid down
by the Indian Roads Congress (IRC) as given in the Rural Roads Manual
(IRC:SP20:2002) will be followed.

|
|
Part
II - Planning, Funding, Execution and Maintenance of Rural Roads
4 Planning for Rural Roads |
|
4.1 Proper
planning is imperative to achieve the objectives of the Programme
within the stipulated time and costs. The Manual for the Preparation
of District Rural Roads Plan and the Core Network, shall be treated
as part of the Guidelines and would stand amended to the extent
modified by the present Guidelines. The Manual lays down the various
steps in the Planning process and the role of different Agencies
including the Intermediate Panchayat, the District Panchayat as
well as the State Level Standing Committee. In the identification
of Core Network, the priorities of elected representatives, including
MPs and MLAs, are expected to be duly taken into account and given
full consideration. The Core Network would constitute the basis
for preparation of project proposals under the PMGSY.
4.2 The District Rural Roads Plan would indicate
the existing road network system in the District and also clearly
identify the proposed roads for providing connectivity to Unconnected
Habitations, in an economic and efficient manner, in terms of cost
and utility. The Core Network will identify the roads required to
assure each eligible Habitation with a Basic Access (single all-weather
road connectivity) to essential social and economic services. Accordingly,
the Core network would consist of some of the existing
roads as well as all the roads proposed for New Connectivity under
the PMGSY.
4.3 In preparing
the District Rural Roads Plan, it would be first necessary to indicate
the weightage for various services. The District Panchayat shall
be the competent authority to select the set of socio-economic /
infrastructure variables best suited for the District, categorise
them and accord relative weightages to them. This would be communicated
to all concerned before commencing the preparation of the District
Rural Roads Plan.
4.4 The Plan
would first be prepared at the Block level, in accordance with the
directions contained in the Manual and the priorities spelt out
by the District Panchayat. In short, the existing road network would
be drawn up, unconnected Habitations identified and the roads required
to connect these unconnected Habitations prepared. This shall constitute
the Block Level Master Plan.
4.5 Once this
exercise is completed, the Core Network for the Block is identified,
by making best use of the existing and proposed road facilities
in such a manner that all the eligible Habitations are assured of
a Basic access. It must be ensured that every Habitation is within
500 metres (1.5 km of Path length in the Hills) of a connected Habitation
or an All-weather road. In drawing up the proposed road links, the
requirements of the people must be taken into account, through the
socio-economic/infrastructure values (Road Index) suitably weighted
(see Para 4.3) and the alignment having the higher Road Index ought
to be considered for selection.
4.6 The Block level Master Plan and the Core Network are then placed
before the Intermediate Panchayat for consideration and approval
of the Core Network. They are simultaneously sent, alongwith the
list of all unconnected Habitations to the Members of Parliament
and MLAs, for their comments, if any. After approval by the Intermediate
Panchayat, the Plans would be placed before the District Panchayat
for its approval. It will be incumbent on the District Panchayat
to ensure that the suggestions given by the Members of Parliament
are given full consideration, within the framework of these Guidelines.
Once approved by the District Panchayat, a copy of the Core Network
would be sent to the State-level Agency as well as the National
Rural Roads Development Agency. No road work may be proposed under
the PMGSY for New Connectivity or Upgradation (where permitted)
unless it forms part of the Core Network.

|
|
5
Funding and Allocation |
|
5.1 Once the
Core Network is prepared, it is possible to estimate the length
of roads for New Connectivity as well as Upgradation for every District.
States may, each year, distribute the State's Allocation among the
Districts giving 80% on the basis of road length required for providing
connectivity to Unconnected Habitations and 20% on the basis of
road length requiring Upgradation under the PMGSY. The District-wise
allocation of funds would also be communicated to the Ministry/NRRDA
every year by the State Government.
5.2 In making
the District-wise allocation, the number of Habitations taken up
under the PMGSY or any other Programme would be excluded from the
total number of Unconnected Habitations (even if the road works
are still under execution). The figures of connected as well as
Unconnected Habitations in any District would keep on changing every
year till such time as all Unconnected Habitations (of the stipulated
population size) have been covered in the District.

|
|
6
Proposals |
|
6.1 The list
of road works to be taken up under the PMGSY will be finalised each
year by the District Panchayat in accordance with the Allocation
of Funds communicated to the District by the State Government (see
Para 5.1). District Panchayat shall finalise the list through a
consultative process involving lower level Panchayati institutions
and elected representatives (see Para 6.5 below) It must be ensured
that the proposed road works are part of the Core Network and that
New Connectivity is given primacy, as indicated in Para 3.1 above.
6.2 It will
be the responsibility of the State Government/District Panchayat
to oversee that lands are available for taking up the proposed road
works. A certificate that Land is available must accompany the proposal
for each road work. It must be noted that the PMGSY does not provide
funds for Land Acquisition. However, the State Governments will
draw up policies so that the process of making land available for
the road works sub-serves the common good and is also just and equitable.
6.3 In drawing
up the list of the road works, the District Panchayat shall ensure
that primacy is accorded to providing New Connectivity to all Unconnected
Habitations. The following Order of Priority shall
be strictly followed.
1 Providing
New connectivity to Unconnected Habitations with a population of
1000 + (500 + in case of Hill States etc)
2 Providing
New connectivity to Unconnected Habitations with a population of
500-999 (250-499 in case of Hill States etc)
3 Upgradation
of Through Routes in the Core network (only Rural Roads to be covered)
4 Upgradation of Link Routes
6.4 The only
exception from the above order of priority is in respect of those
routes that include the Village Panchayat Headquarters or Market
Centres or other educational or medical essential services or those
which are notified as places of tourist interest. In such cases,
provision of new connectivity may be made irrespective of the population
size.
6.5 Under the
PMGSY, the proposals of the Members of Parliament are required to
be given full consideration. The list of Unconnected Habitations
(along with the population) in each District along with the list
of roads identified to connect them as part of the Core Network
should be sent to the Members of Parliament, to facilitate the MPs
in making their suggestions. It will be incumbent upon the District
Panchayat to ensure that, while framing the proposals, full consideration
is given to the proposals received from the Members of Parliament,
within the framework of the Guidelines. For this purpose, the proposals
listed by the Members of Parliament on the PMGSY website (www.pmgsy.org)
would also be taken into consideration.

|
|
7
State level Agencies |
|
7.1 Each State
Government / UT Administration would identify one or two suitable
Agencies (having a presence in all the Districts and with established
competence in executing time-bound road construction works), to
be designated as Executing Agencies. These could
be the Public Works Department / Rural Engineering Service / Organisation
/ Rural Works Department / Zilla Parishad / Panchayati Raj Engineering
Department etc. who have been in existence for a large number of
years and have the necessary experience, expertise and manpower.
No Agency/Consultant shall be created by the States for implementation
of the programmes. In States where more than one Executing Agency
has been identified by the State Government, the distribution of
work would be done with the District as a unit. In other words,
each District will be entrusted to only one Executing Agency. The
Executing Agency will have a Programme Implementation Unit
(PIU) in the District, which should have an officer of
the rank of Executive Engineer as its head.
7.2 Every State
Government / UT Administration shall nominate a Department as the
Nodal Department, who will have the overall responsibility
for implementation of the PMGSY in the State. This would be the
Administrative Department responsible for the Executing Agency entrusted
with the execution of the road works. In the event of there being
two Executing Agencies, the Department responsible for the major
of the two Agencies shall be the Nodal Department. All communication
between the Ministry of Rural Development and the State Government
would be with and through the Nodal Department / State-level Agency.
7.3 The Nodal
Department will identify a State-level autonomous Agency
(Society etc), with a distinct legal status, under its
control for receiving the funds from the Ministry of Rural Development,
as indicated in Para 18 below. If there is no such State-level Agency,
the Nodal Department will take steps to register an Agency under
the Registration of Societies Act, (there should not be more than
one Agency), so as to be able to receive the funds. The Agency will
be headed by the Minister or the Chief Secretary and the Secretary
in charge of the Nodal Department or a senior officer will be the
Chief Executive. All the proposals will be vetted by the Agency
before they are put up before the State-level Standing Committee
and are sent to the NRRDA for clearance by the Ministry of Rural
Development.
7.4 Each State
Government shall set up a State-level Standing Committee
(preferably headed by the Chief Secretary) to vet the Core Networks
and the Project proposals to ensure that they have been formulated
in accordance with the Guidelines. The State Level Standing Committee
would also be responsible for close and effective monitoring of
the Programme, and oversee the timely and proper execution of road
works.

|
|
8
Preparation of Project Proposals and their clearance
|
|
8.1 After
approval by the District Panchayat (refer Para 6.1 above), the proposals
would be forwarded through the District PIU to the State-level Agency
(refer Para 7.3 above). The PIU will at that time prepare the details
of proposals forwarded by the Members of Parliament, and action
taken thereon, in Proformae MP -I and MP -II and
send it along with the proposals.
8.2 The State-level
Agency shall vet the proposals to ensure that they are in accordance
with the Guidelines and shall place them before the State-level
Standing Committee. The size of State project proposals as well
as the time when they would be forwarded to the NRRDA will be as
specified by the Ministry / NRRDA each year.
8.3 The State
Level Standing Committee would scrutinise the proposals to see that
they are in accordance with the Guidelines and that the proposals
of the Members of Parliament have been given full consideration.
After scrutiny by the State Level Standing Committee, the Programme
Implementation Units (PIUs) will prepare the Detailed Project Report
(DPRs) for each proposed road work. The preparation of DPR requires
collection and analysis of data required for the design of Pavement
and Cross-Drainage works such as Inventory and Engineering surveys,
Soil investigations, Hydraulic data etc. The cost of preparation
of DPR @ not more than Rs. 10000 per kilometre may be included in
the Project Cost. Similarly, a fixed amount of not more than Rs.
10000 per kilometre (on actual basis) may be included in the Project
Cost as cost for fixation of Sign Boards, Road Stones and other
Road Furniture as per IRC specifications. Rupees 5000/- per function
for foundation/inauguration ceremonies may also be included. Attached
to the DPR will be a separate Benchmark indicator report giving
status of key indicators of education, health, incomes etc. of each
of the Habitations proposed to be connected (Data from Habitation
Data in Format-I developed for the District Rural Roads Plans/ Census
may be used).
8.4 The PIU
will follow the following Guidelines in preparing the Detailed Project
reports:
(i) The Rural Roads constructed under the Pradhan Mantri Gram Sadak
Yojana must meet the technical specifications and geometric design
standards given in the Rural Roads Manual of the IRC (Publication
IRC:SP20:2002). Most of the new connectivity is likely to carry
traffic of low intensity. It may be noted that the Rural Roads Manual
allows for a carriageway of 3.0m where traffic intensity is less
than 100 motorised vehicles per day and where the traffic is not
likely to increase due to situation, like, dead end, low Habitation
and difficult terrain condition. To ensure economy in respect of
link roads, the carriageway width may be restricted to 3.0m in all
such cases with corresponding reduction in roadway width etc. as
per the Rural Roads Manual.
(ii) The Rural
Roads under the Pradhan Mantri Gram Sadak Yojana will be surface
roads, and, by and large, sealed surface roads. i.e., roads with
a bituminous or cement concrete surfacing. The choice of surface
would be determined, inter alia, by factors like traffic density,
soil type and rainfall, following the technical specifications laid
down in the Rural Roads Manual (IRC:SP20:2002).
(iii) Where
the road work is passing through a Habitation, the road in the Built-up
area and for 50 metres on either side may be so designed that it
is not damaged by water. For this the roads will be designed and
executed as a Cement Road or with Paved Stones, besides providing
side drains. Appropriate side drains will also be provided, so that
improper drainage does not damage the road.
(iv) The Rural
Roads Manual speaks of the advantages of using Modified Bitumen
in place of ordinary Bitumen. Where State Governments have taken
a decision to use Modified Bitumen [including Rubber Modified Bitumen
(RMB)] in any of their Programmes, such use shall be extended also
to the PMGSY roads. The use of Modified Bitumen (including RMB)
would be restricted to Surface Course only (wearing course). Care
should be taken to ensure strict Quality Control, in accordance
with the provisions of IRC Code - IRC53:2002. Special care is to
be taken for quality control by measures such as procuring Bitumen
from the refineries, procurement in bulk and rigorous testing for
quality while applying the Bitumen. All the tests prescribed in
the Rural Roads Manual or by IRC:SP20:2002 or IRC53:2002 shall be
followed.
(v) Wherever
locally available material, including products like Fly Ash are
available, they should be prescribed subject to adherence to technical
norms.
(vi) The Rural
Roads constructed under PMGSY must have proper drainage facilities
As regards the Cross-Drainage works under the Programme, normally
only minor bridges i.e. those having a length of upto 15 metre would
be taken up. Longer bridges would also be admissible under the Programme
but only after inspection by an officer of the rank of Superintending
Engineer or above in case of bridges between 15-25 metres and by
a joint team of the State Technical Agency and senior Engineers
, who shall confirm the need as well as design of the proposed structure.
Due consideration needs to be paid to the cost and benefits accruing
from the bridge. Similarly, in case of the Hill States, the length
of CD works could be longer but the cost of one CD work should not
normally exceed Rs. 25 lakh. The bridges may be so designed as to
serve, where feasible, as Bridge-cum-Bandharas. However, in such
cases, prior commitment of the beneficiary group / village Panchayat
regarding its operation and maintenance should be obtained.

|
|
9
Scrutiny of project proposals
|
|
9.1 Ministry
of Rural Development has identified in consultation with each State
Government, reputed Technical Institutions to scrutinise the project
proposals prepared by the State Governments, provide requisite technical
support to the State Governments, and undertake Quality Control
tests upon specific request. These are being referred to as the
State Technical Agencies (STA). The coordination of activities of
the STAs would be performed by the NRRDA, who may add to or delete
from the list of institutions, as well as to entrust specific tasks
from time to time. The Ministry of Rural Development/ NRRDA may
from time to time identify additional technically qualified agencies
to provide these services to the State Governments and to perform
such other functions as may be necessary in the interest of the
Scheme.
9.2 The PIU
will forward the proposals alongwith the Detailed Project Reports
to the State Technical Agencies for scrutiny of the design and estimates.
The Proformae F-1 to F-8 will form part of the DPR. These will be
forwarded at the level of the Superintending Engineer or the supervising
officer of the PIU, before they are sent to the State Technical
Agencies. A summary of the road works will be prepared in Proforma-'B',
circulated by the Ministry / NRRDA.
9.3 The DPRs
are to be scrutinised by the State Technical Agency (STA) in the
light of the PMGSY Guidelines, IRC specifications as contained in
the Rural Roads Manual / IRC SP20:2002 and the applicable Schedule
of Rates. In doing so, it shall be ensured that no lead charges
would be payable for transportation of soil (except in case of Black
Cotton Soil / Sodic soil). The STA will countersign the Proformae,
whereupon the PIU will forward the same to the State-level Agency.
9.4 The State-level
Agency will consolidate the proposals from each PIU, after verifying
that they have been duly scrutinised by the respective STAs. They
will then prepare the State Abstract and send all the Project proposals
to the NRRDA alongwith the proformae MP-I and MP-II of each District
as well as the proformae.
9.5 The NRRDA
will thereupon scrutinise the proposals from the State Level Agency
to ensure that the proposals have been made duly keeping in view
the Programme Guidelines and that they have been duly verified by
the STAs. The proposals for each State would then be put up before
the Empowered Committee for consideration.

|
|
10
Empowered Committee
|
|
10.1 At the
Central level, the Project proposals received from the State Governments
would be considered by an Empowered Committee, to be chaired by
Secretary, Department of Rural Development. The representatives
of the State Government, whose projects are being considered by
the Empowered Committee, may be invited to attend the Meetings,
as and when required. The Recommendations of the Empowered Committee
would, thereafter, be submitted to the Minister of Rural Development
for clearance.
10.2 The Ministry
will communicate the clearance of the Proposals to the State Government.
It may , however, be noted that clearance by the Ministry does not
imply Administrative or Technical sanction of the proposals. The
well established procedures of the Executing Agency / ies in this
regard would continue to be followed.
10.3 Once approved, the alignment of the road should not be changed
without obtaining the concurrence of the District Panchayat, the
State Technical Agency and the State level Standing Committee.

|
|
11
Tendering of works
|
|
11.1 After
the project proposals have been cleared by the Ministry, the Executing
Agency would invite tenders and commence work on the projects. The
well-established procedure for tendering, through competitive bidding,
would be followed for all projects. All the projects scrutinised
by the STA and cleared by the Ministry, will be tendered as such,
and no changes shall be made in the work. The States will follow
the Standard Bidding Document, prescribed by the Ministry of Rural
Development, for all the tenders.
11.2 All State
level formalities relating to issue of tender notice, finalisation
of tender and award of works should be completed within 120 days
of clearance of the project proposals failing which it will be deemed
that the works in question have been cancelled. A report on the
circumstances in which the work could not be awarded must be sent
to the National Rural Roads Development Agency (NRRDA). The State
Government would also stand to lose that amount.
11.3 In case
the value of tenders received is above the estimate that has been
cleared by the Ministry, the difference (tender premium) will be
borne by the State Government.

|
|
12
Programme Implementation Units
|
|
12.1 At the
District level, the Programme will be co-ordinated, and implemented
through the Executing Agencies. While, for all the Districts, it
is desirable that a dedicated Programme Implementation Unit
(PIU) is set up, this is especially desirable for all States
having an annual Allocation of Rs. 75 crore or more per annum under
the PMGSY, and all the participating States in the externally aided
projects. The Programme Implementation Unit at the District Level
may typically be headed by an Engineer not below the rank of Executive
Engineer. All PIUs will be manned by competent technical personnel
from amongst the available staff or through deputationists. No new
posts will be created for the purpose. In other States, the PMGSY
works will be executed by the Executive Engineers. The Executive
Engineer as well as the heads of PIU (as the case may be) will be
designated as officers of the State Level Agency, so as to enable
them to operate on the funds of the Agency.
12.2 All staff
costs will be borne by the State Government. The Pradhan Mantri
Gram Sadak Yojana does not provide for any staff costs.
12.3 No Agency
charges will be admissible for road works taken up under this Programme.
The Executing Agencies will not levy charges in any form, such as
Centage charges etc. Expenditure on foundation and inauguration
ceremonies to be done by MPs, upto Rs. 5,000 per function, may however
be charged to the project.

|
|
13
Execution of Works
|
 |
13.1
The relevant projects would be executed by the PIUs and completed
within a period of 6 months, from the date of issue of the
Work order. Delayed execution of projects, could adversely
affect clearance of the proposals in subsequent years. PMGSY
does not provide for any cost over-runs.
13.2
Except for Hill States, the Road works under the PMGSY shall
not be taken up in stages. Once road works are taken up, they
should be completed to the requisite Technical Specifications
in the prescribed time-frame.
|
13.3 In case
of the Hill States (North-East (except Assam), Sikkim, Himachal
Pradesh, Jammu & Kashmir, Uttaranchal) and the Andaman &
Nicobar Islands, however, two working seasons- about 18 months -
may be allowed to the Executing Agency to complete the projects
cleared by the Ministry of Rural Development under the Programme.
This is to enable the formation to stabilise during one season,
followed by Metalling and surfacing in the subsequent working season.
13.4 Any cost
over-run, either due to time over-run or for any other reason whatsoever,
would have to be borne by the State Government. To avoid such a
contingency, the Executing Agency will incorporate suitable Penalty
Clauses, as indicated in the Standard Bidding Document.
13.5 An important
principle of the Pradhan Mantri Gram Sadak Yojana is the assured
availability of funds, so as to facilitate timely completion of
road works. It shall be the responsibility of the Executing Agencies
to ensure timely payments to the contractors, subject to satisfactory
execution of work. Delays, in payment due, should be avoided.
13.6 To maintain
quality and to ensure timely completion of works, the Ministry of
Rural Development may lay down a scheme of incentives/disincentives
to the States.

|
|
14
National Rural Roads Development Agency
|
|
14.1 The Ministry
of Rural Development have set up the National Rural Roads Development
Agency (NRRDA) to provide Operational and Management support to
the Programme. The NRRDA will provide support, inter alia, on the
following:
(i) Designs & Specifications and Cost norms.
(ii) Principal Technical agencies (PTAs) and State Technical Agencies
(STAs)
(iii) District Rural Roads Plans and Core Network.
(iv) Scrutiny of Project Proposals
(v) National Quality Monitors
(vi) Monitoring of progress of the PMGSY
(vi) On-Line Management & Monitoring System
(vii) Training, Workshops, Research, Pilot Projects and Literature.
(viii) Human Resource Development
14.2 In respect
of the Pradhan Mantri Gram Sadak Yojana, all State Governments /
UT Administrations will ensure timely furnishing of all necessary
reports, data and information to the National Rural Roads Development
Agency.

|
|
15
Quality Control and Supervision of Works
|
|
15.1
Ensuring the quality of the road works shall be the responsibility
of the State Governments/ Union Territory Administrations,
who are implementing the Programme. To this end, all works
will be effectively supervised. The Quality Control Register
prescribed by the NRRDA shall invariably be maintained for
each of the road works. Payment shall not be made to the Contractor
unless the tests have been found to be successful. The record
of tests shall be computerised on the format prescribed by
the NRRDA. |  |
15.2 The roads
constructed under this Programme are expected to be of very high
standard, requiring no major repairs for at least five (5) years
after completion of construction. In order to realise this objective,
suitable clauses relating to Performance Guarantee/routine maintenance
shall be included in the Contract Documents, as per the provisions
in the Standard Bidding Document. In particular, the State Government
shall obtain a Bank Guarantee from the Contractor for 10% of the
value of the work, which should remain valid for the 5 year period
and should be discharged only after consulting the Panchayati Raj
Institution responsible for maintenance (See Para 17.1).
15.3 A three-tier
Quality Control mechanism is envisaged under the Pradhan Mantri
Gram Sadak Yojana. The State Governments would be responsible for
the first two-tiers of the Quality Control Structure, and would
also bear the cost of the two tiers at the District and the State
level. The PIU or the Executive Engineer will be the first tier,
whose prime responsibility will be to ensure that that the all the
materials utilised and the workmanship conform to the prescribed
specifications. They shall also ensure that all the tests prescribed
by the National Rural Road Development Agency, are carried out at
the specified time and place by the specified person/ authority.
15.4 As the Second-tier of the Quality Control Structure, periodic
inspections of works will be carried out by Quality Control Units,
set up / engaged by the State Government, independent of the Executive
Engineers / PIUs. These officers/ Agencies would be expected to
carry out random tests and also get samples of material used tested
in laboratories of the State Government as well as, in certain cases,
independent laboratories, say those of the State Technical Agencies.
The State Governments will issue the requisite guidelines in this
regard.
15.5 It shall
be mandatory to record, in the relevant module of the On-line Management
& Monitoring System (OMMS) , all the test results carried out
by the two-tiers indicated above.
15.6 Each State
government / UT Administration will appoint a senior Engineer (not
below the rank of Superintending Engineer) to function as State
Quality Coordinator at the State level. His / her function
will be to oversee the satisfactory functioning of Quality control
mechanism within the State / UT. This function would also involve
overseeing the follow up action on the reports of the National Quality
Monitors. The Quality Coordinator should be part of the State level
Agency.
15.7 As the
third-tier of the Quality Control Structure, the NRRDA will engage
Independent Monitors (Individuals / Agency) for inspection, at random,
of the road works under the Programme. These persons are designated
as National Quality Monitors (NQM). It will be the responsibility
of the PIU to facilitate the inspection of works by the NQM, who
shall be given free access to all records, administrative, technical
and financial.
15.8 The National
Quality Monitors, shall inspect the road works with particular reference
to Quality. They may take samples from the site and get them examined
by any competent Technical Agency / Institution. They shall also
report on the functioning of the Quality Control mechanism in the
District. The Monitors shall submit their report to the NRRDA, through
the medium of the On-line Management & Monitoring System. The
reports of the NQMs will be sent by NRRDA to the State Government
for appropriate action within period to be specified. In respect
of works-in-progress, in case quality check reveals 'Poor' or 'Average'
work, the State Government shall ensure that the contractor replaces
the material or rectifies the workmanship (as the case may be) within
the time period stipulated. In respect of NQM Reports, the State
Government shall, each month, report on the action taken on each
of the Reports pending with the State Government. All works rated
'Poor' and 'Average' during work-in-progress shall be re-inspected
by an NQM after a rectification report has been received from the
State Government.
15.9 The State
Governments / UT Administrations shall put in place systems to identify
and take appropriate action (including blacklisting in serious cases)
against the Contractors and the Field Engineers who are found negligent
in ensuring the quality of road works. Where the completed work
of a Contractor is found to be 'Poor' or 'Average', the Contractor
concerned shall be blacklisted by the State and no PMGSY works are
to be given to such Contractor in future. States/ UTs should also
consider blacklisting such Contractors for works under other State
Government programmes. The State Governments / UT Administrations
shall ensure that all the PMGSY road works qualify to be rated at
least as 'Good' during implementation and 'Very Good' when completed.
15.10 The On-line
Management & Monitoring System has a provision by which a 'Red
Pole' would appear against a work if any of the tests on that road
work are unsuccessful. Similarly where the NQM finds that the quality
of the Work is 'Poor' or 'Average', a Red Flag appears against the
work. In case of a Red Pole, the payment shall not be made unless
the work is rectified and the tests are successful. In case of a
Red Flag, the payment shall not be made unless the Superintending
Engineer (Supervisory Engineer to the PIU in case of PIUs) inspects
the work and is satisfied that all the defects have been rectified.
15.11 Recurrent
adverse reports about quality of road works in a given District
/ State might entail suspension of the Programme in that area till
the underlying causes of defective work have been addressed.
15.12 The State Quality Coordinator/ Head of PIU shall be the authority
to inquire into complaints/representations in respect of quality
of works and they would be responsible for sending a reply after
proper investigation to the complainant within 30 days. The State
Level Agency shall monitor the disposal of complaints and the NRRDA
shall liaise with the State Level agencies to ensure prompt attendance
of all complaints/representations.

|
|
16
Monitoring
|
 |
16.1
Effective monitoring of the Programme being critical, the
State Governments / UT Administrations will ensure that the
officials are prompt in sending the requisite reports / information.
to the State level Agency as well as the NRRDA. The On-line
Management & Monitoring System will be the chief mechanism
for monitoring the Programme. To this end, the officials are
required to furnish, 'on line', all the data and information,
as may be prescribed by the NRRDA from time to time, in the
relevant module of the On-line Management & Monitoring
System. |
They shall
be responsible for uninterrupted maintenance of the Computer Hardware
and Software as well as the Internet connectivity. The Software
for the OMMS shall be supplied by the NRRDA and it shall not be
modified at any level in the States; any requirement or suggestion
for change shall be intimated to the NRRDA. In case of continued
failure to update data on the OMMS, further releases to the State
could be affected.
16.2 The State
Government should provide necessary manpower, space and facilities
to set up the Computer Hardware at the District and State Level
apart from ensuring regular and timely feeding of data. Since most
of the data would reside on the State Servers, the State level Agency
must ensure that the State Server is functional all 24 hours.
16.3 It shall
be the responsibility of the Executive Engineer / Head of the PIU
to ensure effective up-time of the Hardware and also the Internet
connectivity, with the State Server and the Central Server, of the
Client Machines at the PIU/ District level. He /she shall be responsible
for the constant updating and accuracy of data relating to the progress
of road works, record of Quality control tests as well as the payments
made. The data shall be updated as warranted but at least once a
week. He /she shall also ensure that the photographs and video clips
of each road work are regularly, and at least once every month,
uploaded into the System.
16.4 Each State
government would identify one officer of sufficient seniority and
having adequate knowledge of Information Technology to function
as State IT Coordinator. His / her function will
be to oversee the regularity and accuracy of the data being furnished
by the Districts. The IT Coordinator, who shall form part of the
State-level Agency, shall also be responsible to oversee the upkeep
of the Hardware and Software as well as the training requirements
of the personnel dealing with the PMGSY.
16.5
The District Vigilance and Monitoring Committee set up by the Ministry
will also monitor the progress and exercise vigilance in respect
of PMGSY.

|
|
17
Maintenance of Rural Roads
|
|
17.1 While
submitting the project for approval, each State Government / UT
Administration shall identify a suitable Panchayati Raj Institution
(District Panchayat/ Intermediate Panchayat), for undertaking the
maintenance of the entire Core network and particularly the road
works constructed / upgraded under this Programme. The State Government
should issue necessary instructions to associate the identified
Panchayati Raj Institutions with the execution of the work at all
stages, especially submission of periodic reports relating to progress
and quality of works. The State Authorities will be required to
furnish an Undertaking that they would remit (to the identified
Panchayati Raj Institution), from the State Government funds, the
requisite cost of Maintenance. The State Governments will also offer
an Undertaking for the release of maintenance costs, alongwith their
project proposals. The Ministry of Rural Development would oversee
the implementation of this undertaking. It shall be open to the
State Governments / Panchayati Raj Institutions to develop sustainable
alternative sources of funding for undertaking the Maintenance function.
It must be emphasised that given the huge quantum of investment
involved in the Programme, the specification and enforcement by
the State Governments of a satisfactory mechanism to provide funding
and other assistance for the proper maintenance of the PMGSY assets
will be key to continuance of the Programme in that State.
17.2 The Rural
Roads will be handed over by the PIU, on completion of the contract
(including guarantee/maintenance period of 5 years), to the designated
Panchayati Raj Institution for Maintenance, and a separate report
will be made in all such cases under OMMS giving the name of the
PRI and the date of its taking over.

|
|
Part
III - Flow of funds, procedure for release and Audit
18 Flow of Funds
|
|
18.1 The State-level
Agency (refer Para 7.3 above) shall select a branch with internet
connectivity at the State Headquarters, of any Public Sector Bank
or Institution based Bank for maintaining an Account of the Pradhan
Mantri Gram Sadak Yojana. Once selected, the Account shall not be
changed to any other Branch or Bank. There will be a written undertaking
from the Bank that it will follow the Guidelines of Government of
India for payments from the PMGSY Funds. The concerned branch will
maintain Internet connectivity and enter the data into the relevant
module of the On-line Management & Monitoring System.
18.2 The State
level Agency will communicate to the NRRDA and to the Ministry the
details of the Bank branch and the Account number. The Ministry
of Rural Development shall release the funds, only into this Account,
on the recommendation of the NRRDA, who shall satisfy themselves
that the requirements in the Guidelines have been met.
18.3 The State level Agency will maintain only one Account for PMGSY
funds, from which all payments will be made These shall relate to
the Programme expenditure on road works. No other administrative
expenditures (such as purchase of vehicles and office equipment)
shall be debitable to this account.
18.4 The Programme
expenditure will be regulated as follows:
18.4.1. There
will not be separate bank accounts of PIUs for Programme expenditure.
As indicated in Para 12.1 above, the Executive Engineers of PIUs
/ Heads of PIUs (who are the drawing and disbursing officers of
the PIU) will be declared as the ex-officio members of the Agency,
so as to enable them to draw on the funds of the Agency from the
Programme Account. They shall be the Authorised signatories
for issuing cheques.
18.4.2 The
Agency would nominate one of its senior officers, normally the Finance
Controller, or an officer not below the rank of a Chief Engineer,
as the Empowered Officer. It shall be open only to the Empowered
Officer to inform the Bank of the names of Authorised Signatories,
for issuing cheques on the Agency's bank account.
18.4.3 The
Empowered Officer will furnish this list of Authorised Signatories
(Executive Engineers of Districts / Heads of PIUs) to the Bank,
apart from himself maintaining a record of it. This list will be
periodically verified to ensure its accuracy. The Bank will issue
separate Cheque Books to each of the Authorised Signatories, and
will keep their signatures on record.
18.4.4 The Empowered Officer will also inform the Bank of the names
of Authorised Payees (contractors and suppliers
with whom Agreements have been duly entered into, as well as Statutory
Authorities, such as ITO etc) and their designated payee accounts,
and also the amounts that are admissible against each of the Contractors
and suppliers. This will be in conformity with the Work Agreements.
The Empowered Officer may lay down suitable limits on monthly payments
in line with the agreed Works Programme for the respective packages.
Standing instructions will be issued to the Bank Branches by the
Empowered Officer in this regard.
18.4.5 The
Authorised Signatories will make payments, as per the established
procedure, by Account Payee cheque mentioning the designated payee
accounts. They will immediately enter the cheque and payee details
in the Payment Module of the OMMS.
18.4.6 On presentation
of the cheque, the Bank would satisfy itself that the payment details
have been entered in the Payment Module, and that the cheque meets
with all other requirements, among others, like signatures agreeing
with specimen signatures, the cheque amount being within the balance
authorised limit, and the payee being the authorised payee, payee
account details being fully and correctly specified etc.
18.4.7 The
Bank will not allow the funds to be used by any person other than
the authorised signatories and for any purpose other than the authorised
payment for Works taken up under the PMGSY. Nor will it be open
to the State level Agency to invest these funds in any other Bank
/ Branch, whether for short or medium term, including under Fixed
Deposits.
18.4.8 The
Bank will render monthly account, in respect of PMGSY Funds, to
the PIU, the State level Agency and the National Rural Roads Development
Agency .
18.4.9 A tripartite
Memorandum of Understanding will be entered into between the Bank,
State-level Agency and the Ministry of Rural Development wherein
the parties would agree to abide by the provisions of the Guidelines.
In particular, the Bank will agree to abide by the instructions
issued, from time to time, by the Ministry of Rural Development
/National Rural Roads Development Agency (NRRDA) regarding the operation
of the Account.
18.5 The NRRDA
may, from time to time, issue such directives as necessary for smooth
flow of funds and effectiveness of the Programme.
18.6 The Accounting
System to be prescribed by the NRRDA, which would be largely based
on the well-established Accounting system of the Works Departments,
would be utilised for this Programme.
18.7 Money
accruing as Interest will be added to the PMGSY funds. The expenditure
out of this interest amount will be guided by the instructions /
guidelines to be issued by the Ministry of Rural Development / NRRDA
from time to time. The Bank shall intimate to the State level Agency
as well as NRRDA, the interest amount credited by it to the Account
from time to time.

|
|
19
Procedure for Release Of Funds to the State level Agency
|
|
19.1
Since the PMGSY has adopted a Project approach where road
works have to be completed within a stipulated time-limit,
the cost of the projects cleared for a State for each Phase
of the PMGSY will be made available to the State level Agency
in suitable instalments (upto four instalments).
19.2
The first instalment in a particular year amounting to 25%
of the value of projects cleared by the Ministry shall be
released after the project has been cleared by the Ministry
and the release of remaining instalments would be subject
to utilisation of 60% of the total available funds as well
as completion of at least 80% of the road works upto the (but
not including) the year previous to the current year and fulfilment
of other conditions, if any, stipulated while releasing the
previous instalment. Total available funds will be the funds
available (including interest accrued) with the State-level
Agency at the time of the release of the previous instalment
/ plus the amount of the previous instalment.
|  |
19.3 For release
of every instalment (except the first ), conditions prescribed at
A and B below will require to be met while those at C and D are
one-time conditions to be met. The Conditions are as follows:
A. Utilisation Certificate for the Funds released earlier. The Utilisation
Certificate shall be in the form prescribed.
B. A Certificate by the Bank Manager, indicating the balance amount
on the date of issue of the Certificate (this should tally with
the on-line data).
C. A Certificate that works which were sanctioned more than two
years earlier have been duly completed and the funds released for
such works have also been fully utilised.
D. For all releases after October of every year, production of an
Audited Statement of Accounts and a Balance Sheet, duly certified
by a Chartered Accountant for the accounts of the previous financial
year.
19.4 For the
purpose of releasing funds, the State would be the Unit.

|
|
20
Audit
|
|
20.1 The State
level Agency will ensure that the accounts are audited by a chartered
accountant of standing within six months of the close of the financial
year. This account will be supported by a statement of reconciliation
with the accounts of PIUs and a certificate of Chartered Accountant
on its accuracy.
20.2 In addition to the Audit by the Chartered Accountant, the works
under this Programme would be subject to audit by the Office of
the Comptroller and Auditor-General of India (C&AG). The Audit
of the work done by the C&AG may cover aspects of quality, in
addition to financial audit.
20.3 Both the
State level Agency and the PIUs must provide all information to
District level Vigilance and Monitoring Committees and the Panchayati
Raj Institutions.

|
|
21
Miscellaneous |
|
21.1 The National
Rural Roads Development Agency (NRRDA) will designate reputed Technical
and Research Institutions such as the Indian Institutes of Technology
as Principal Technical Agencies, to provide technical
support and to take up research projects, study and evaluate different
technologies and advise on measures to improve the quality and cost
norms of Rural Roads
21.2 Within
15 days of the date of Work Order or at the time of laying of the
Foundation Stone for a road work (whichever is earlier), the Signboards
along with the Logo of the PMGSY should be erected at the site of
road works. The Signboards should indicate the name of the Programme
(PMGSY), name of the road, its length, estimated cost, date of commencement
and completion of construction, name of the executing contractor
and the Panchayati Raj Institution maintaining it. It is desirable
that this is in the form of a permanent brick-masonry/ concrete
structure at both ends of the road
21.3 The National
Rural Road Development Agency may, in co-operation with the State
level Agency, organise suitable Training Programmes for the PIU
personnel.
21.4 Planting
of fruit bearing and other suitable trees, on both sides of the
roads would be taken up by the State Governments / UT Administration
from their own funds.
21.5 The Ministry
of Rural Development may, from time to time, issue such directions
as may be necessary for smooth implementation of the Programme.

|
|
22
Convergence |
|
22.1 Rural
connectivity is not an end in itself. It is a means. It is expected
that the connectivity will improve indicators of education, health,
rural incomes etc., provided as a follow up, and in consultation
with the local Panchayati Raj Institutions, convergence is achieved
with other ongoing Programmes in these sectors. It is expected that
the District Panchayat will focus on these issues. Before the start
of work on Rural Roads, the bench mark indicators may be measured
and attached to the detailed project report.
22.2 The NRRDA
will provide 100% assistance for independent Studies to establish
the impact of the new rural connectivity in a District from time
to time.

|